Study guide · Domain 3
Agile Frameworks/Methodologies
20% of the exam's questions · 5 tasks
Agile frameworks and methodologies is a fifth of the scored questions. It asks when an adaptive approach fits, how iterations are planned and tracked, which artifacts an adaptive team uses to stay in control, what makes Scrum, Extreme Programming (XP), Kanban and scaled frameworks such as SAFe different, and how a team defines done and orders its work by value. Questions usually describe a team at work (a sprint planning session, a burndown that flattens, a product owner reordering the backlog) and ask which event, role, artifact or practice it is, or what the team member should do. Know the Scrum roles, events and artifacts exactly, know that velocity is one team's own planning measure, and keep acceptance criteria (per item) apart from the Definition of Done (for every item).
A study feature written by ExamDragon, not part of the real exam. Each heading is one of PMI's 5 tasks for this domain, in our own words. Predictive, adaptive and hybrid approaches run through every domain (PMI: "not isolated to any particular domain or task").
At a glance
Domain 3of the exam's questions (PMI)
- Tasks
- 5
- Key terms
- 14
What this guide covers, task by task
- AGL.1Know when an adaptive approach suits the work and the organisation
- AGL.2Plan iterations: slice the work, set the scope inputs and track progress the adaptive way
- AGL.3Keep an adaptive project under control with its own artifacts
- AGL.4Know the parts of the common adaptive frameworks: Scrum, XP, Kanban and scaled agile
- AGL.5Define what done means for adaptive work and put tasks in order of value
AGL.1Know when an adaptive approach suits the work and the organisation
- An adaptive approach suits work with uncertain or changing requirements, where early feedback is valuable, the product can be delivered in usable pieces, and customers or users are available to review it often.
- Pros: early and frequent value, fast learning, change welcomed at low cost, risk reduced by delivering small pieces. Cons: less certainty about final scope and cost up front, a need for close customer involvement, and discipline the team must sustain.
- Predictive pros and cons are the mirror image: certainty and documentation up front, but late feedback and costly change.
- Structures that help: small, cross-functional, colocated or well-connected teams with authority to decide how they work; strong hierarchies and heavy approval chains slow adaptive work, though virtual teams can work well with the right tools.
- Enterprise environmental factors (conditions outside the team's control, such as culture, leadership support, regulation, tools and market) and organisational process assets (the organisation's own templates, policies, lessons learned and knowledge bases) can help or hinder an adaptive approach.
- Hybrid is common: an adaptive approach for the uncertain parts and a predictive one for the fixed parts, joined by shared milestones.
- Predictive
- A predictive approach is the better fit when requirements are known and stable and change after delivery would be very costly.
- Adaptive
- An adaptive approach is the better fit when the customer can only say what they want after seeing something work, and the team can deliver and learn in short cycles.
- In practiceA bank wants a new budgeting feature in its mobile app but is not sure which tools customers will use. Kenji, a business analyst, notes that the requirements will only become clear from customer feedback and that the feature can be released in small parts. He recommends an adaptive approach with two-week iterations and a customer panel reviewing each increment. The bank's culture of monthly approval meetings is an environmental factor the team flags, asking the sponsor to delegate decisions on the backlog to a product owner.
- Where questions turnChoosing agile because it sounds modern. The choice follows the work: stable, costly-to-change work suits predictive; uncertain, valuable-to-learn work suits adaptive.
AGL.2Plan iterations: slice the work, set the scope inputs and track progress the adaptive way
- An iteration (a sprint in Scrum) is a fixed timebox, commonly one to four weeks, that produces a usable increment that meets the Definition of Done; releases group the results of one or more iterations for delivery to users.
- Iteration planning picks the highest priority backlog items the team believes it can complete, using its velocity and capacity, and breaks them into tasks; the iteration's length does not change once it starts.
- Pros of short iterations: frequent feedback, a regular rhythm, early value and risk exposed early. Cons: overhead from frequent events, and work that cannot be split may not fit a single timebox.
- The predictive WBS translates into an adaptive hierarchy: the product vision, then epics (large bodies of work), then features, then user stories small enough to finish in one iteration, then tasks.
- Inputs for scope: the product vision, the roadmap, the product backlog with its priorities, stakeholder feedback from reviews, and the team's Definition of Done; backlog refinement keeps the top of the backlog ready.
- Adaptive tracking measures working results each iteration (completed stories, velocity, burndown) rather than percent complete against a long schedule, so problems show up within days.
- Predictive
- Predictive tracking compares progress with a baseline schedule and budget and often only shows a problem at a reporting period or a gate.
- Adaptive
- Adaptive tracking shows progress daily (task board, burndown) and per iteration (velocity, review of the increment), so the plan adjusts quickly.
- In practiceA telecom team's velocity over its last three sprints was 28, 32 and 30 points. For the next sprint the product owner brings 45 points of top priority stories. Ana, a developer, points out that the team's average is 30 points and one of the team's five developers is away for half the sprint, about a tenth of its capacity. The team selects about 27 points of the top items and leaves the rest in the backlog. Planning from its own velocity and capacity keeps the sprint forecast realistic.
- Where questions turnExtending a sprint to finish unfinished work. The timebox is fixed; unfinished items go back to the product backlog to be reordered.
AGL.3Keep an adaptive project under control with its own artifacts
- The product backlog is the single ordered list of everything the product might need, owned by the product owner; the sprint backlog is the sprint goal, the items selected for the sprint and the developers' plan to deliver them; the increment is the sum of done work.
- A burndown chart shows work remaining against time in the iteration or release; a burnup chart shows work completed and total scope, so a scope increase is visible as a rising scope line.
- A task or Kanban board shows each item's state (for example to do, in progress, done); a cumulative flow diagram shows how many items are in each state over time, so a widening band reveals a bottleneck.
- Information radiators are large, visible displays (boards, charts) placed where everyone can see them, replacing many written status reports.
- Other controls: the Definition of Done, acceptance criteria on each item, the team's working agreements, the impediment list, and actions agreed in the retrospective.
- Velocity is the amount of work a team completes per iteration in its own units; it is for that team's planning, not for comparing teams or judging individuals.
- Predictive
- Control artifacts are documents and baselines: schedules, variance reports, change logs and status reports.
- Adaptive
- Control artifacts are light and visible: the backlogs, the board, burndown and burnup charts and the increment itself, reviewed at the team's regular events.
- In practiceHalfway through a sprint at a logistics software firm, the burndown line is flat for three days. At the daily scrum the developers raise that the test environment is down. Tomas, the scrum master, takes the impediment away to resolve with the infrastructure team. The chart did its job: a flat line showed a problem early enough to act within the sprint.
- Where questions turnBlaming the team when a burnup shows a later forecast finish. Check both lines: if the completed-work line is climbing at its usual rate and the scope line has risen, the added scope, not the team's pace, pushed the finish out.
AGL.4Know the parts of the common adaptive frameworks: Scrum, XP, Kanban and scaled agile
- Scrum has three accountabilities (product owner, scrum master, developers), five events (the sprint, sprint planning, the daily scrum, the sprint review and the sprint retrospective) and three artifacts (product backlog, sprint backlog, increment).
- The product owner maximises value and orders the backlog; the scrum master coaches the team and the organisation in Scrum and removes impediments; the developers create the increment and decide how to do the work.
- The sprint review inspects the increment with stakeholders and adapts the backlog; the retrospective inspects how the team worked and agrees improvements. Do not mix them up.
- Extreme Programming (XP) focuses on engineering practice: pair programming, test-driven development (write the test first), continuous integration, small releases, refactoring, collective code ownership and a sustainable pace.
- Kanban manages flow without fixed iterations: visualise the work on a board, limit work in progress (WIP) per column, manage and measure flow (lead time, cycle time) and improve continuously; work is pulled when capacity frees up.
- SAFe (Scaled Agile Framework) coordinates many agile teams: teams of teams form an agile release train, which plans together in program increment (PI) planning, typically every 8 to 12 weeks; Lean is the wider idea of maximising value and removing waste.
- Predictive
- Some predictive organisations adopt single practices such as daily stand-ups or a Kanban board for operations work without becoming adaptive overall.
- Adaptive
- Teams choose the framework that fits: Scrum for product work in sprints, Kanban for continuous flow such as support requests, XP practices for software quality, SAFe when many teams build one product.
- In practiceA help desk team at a university receives requests at unpredictable times and found two-week sprints awkward because urgent tickets arrived mid-sprint. Grace, the team lead, suggests Kanban: a board with columns for new, in progress, waiting and done, a limit of four items in progress, and weekly review of cycle time. Work is pulled as soon as someone has capacity. The approach fits because the work is a continuous flow rather than planned batches.
- Where questions turnCalling the scrum master the team's manager, or saying the product owner assigns tasks. The scrum master serves and coaches; the developers decide who does what.
AGL.5Define what done means for adaptive work and put tasks in order of value
- Acceptance criteria are the conditions a specific backlog item must meet to be accepted by the product owner; the Definition of Done is the shared quality checklist that applies to every item (for example code reviewed, tested, documented).
- An item is done only when it meets both its acceptance criteria and the Definition of Done; partly done work is not counted in velocity or shown as complete in the review.
- Success for adaptive work means delivered value: working increments that users accept, outcomes measured, not just tasks ticked off.
- The product owner orders the backlog by value, risk, dependencies and learning; the team advises on effort and dependencies.
- MoSCoW sorts items into must have, should have, could have and won't have this time; other aids are value versus effort, the Kano model (basic, performance and delight features) and weighted shortest job first in SAFe.
- During the iteration the team self-organises: members pull tasks rather than being assigned them, limit how much is in progress, and swarm on blocked items to finish what is started.
- Predictive
- Predictive task management assigns activities from the schedule and measures percent complete; acceptance happens mostly at the end.
- Adaptive
- Adaptive task management pulls tasks from the sprint backlog, finishes one before starting another, and accepts work item by item against its criteria.
- In practiceA retail team finishes the 'Save a wish list' story, and the product owner, Farah, checks it against its acceptance criteria: a signed-in shopper can add an item, see the list and remove an item. All pass, but the automated tests required by the Definition of Done have not been written. The story is not done, so it is not shown as complete in the sprint review. The team writes the tests first, because the Definition of Done applies to every item.
- Where questions turnTreating acceptance criteria and the Definition of Done as the same thing. Acceptance criteria belong to one item; the Definition of Done applies to all of them.
Key terms
- Product backlog
- The single ordered list of everything the product might need, owned by the product owner.
- Sprint backlog
- What the developers take on for the sprint: its goal, the backlog items chosen and their plan for delivering them.
- Increment
- A concrete, usable step toward the product goal that meets the Definition of Done and adds to every earlier increment; a sprint can produce more than one.
- Product owner
- The person accountable for maximising the product's value and for ordering the product backlog.
- Scrum master
- The person accountable for the team's effectiveness with Scrum, who coaches and removes impediments.
- Sprint retrospective
- The event at the end of a sprint where the team inspects how it worked and plans improvements.
- Velocity
- The amount of work one team completes per iteration, used by that team to plan.
- Burndown chart
- A chart of work remaining against time in an iteration or release.
- Burnup chart
- A chart of work completed against time, with a separate line for total scope.
- WIP limit
- The maximum number of items allowed in a stage of a Kanban board at once.
- Definition of Done
- The shared checklist of quality conditions every item must meet to be called done.
- Acceptance criteria
- The conditions a specific backlog item must meet to be accepted.
- Agile release train
- In SAFe, a long-lived team of agile teams that plans and delivers together.
- Test-driven development
- An XP practice of writing an automated test before the code that makes it pass.
After this guide: Given a short scene from an adaptive team, can you name the role, event, artifact or framework at work, read a burndown or a board, plan from the team's own velocity, tell acceptance criteria from the Definition of Done, and order work by value?
Practise Agile Frameworks/MethodologiesExamDragon is independent exam preparation, not affiliated with, endorsed by, approved by or reviewed by the Project Management Institute (PMI). CAPM and PMI are registered marks of the Project Management Institute, Inc. The names are used only to describe the exam. Every question and guide here is our own, written from PMI's published CAPM Examination Content Outline (2023 Exam Update); the path is not a source of the 23 hours of project management education PMI requires.