Study guide · Domain 2

Predictive, Plan-Based Methodologies

17% of the exam's questions · 3 tasks

Predictive, plan-based methodologies is about a sixth of the scored questions. It asks when a plan-driven approach fits, what happens in each process group (initiating, planning, executing, monitoring and controlling, closing), how a schedule is built from the work breakdown structure through to the critical path, and how a predictive project is kept under control with its logs, baselines, change control and earned value figures. Expect calculations at the associate level: a small network with durations and predecessors to find the critical path or the float, and an earned value table to compute a variance or an index and say what it means. Read the figures carefully, use the formula exactly, and interpret the sign: a negative variance or an index below 1 is unfavourable.

A study feature written by ExamDragon, not part of the real exam. Each heading is one of PMI's 3 tasks for this domain, in our own words. Predictive, adaptive and hybrid approaches run through every domain (PMI: "not isolated to any particular domain or task").

PRD.1Know when a plan-driven, predictive approach suits the work and the organisation

  • A predictive approach suits work whose requirements are clear and stable, where change late is costly, where regulation or contracts demand a defined scope and documentation, and where the deliverable cannot be used in pieces (a bridge, a plant, a regulated device).
  • Organisational structure matters: in a functional organisation the functional manager holds authority and the project manager is weak; in a matrix (weak, balanced, strong) authority is shared; in a projectized organisation the project manager has most authority. Predictive work is common in hierarchical and functional structures.
  • Colocated teams communicate face to face easily; virtual teams need deliberate communication tools and a clear plan, which a predictive approach's written plans support.
  • The five process groups: initiating (charter, stakeholder identification), planning (scope, schedule, cost, quality, risk and other plans, baselines), executing (doing the work, managing the team, quality assurance), monitoring and controlling (measuring performance against the baselines, change control) and closing (acceptance, handover, lessons learned).
  • Process groups are not phases: each phase can run through all five, and monitoring and controlling runs across the whole project.
  • Project components: phases and phase gates (a decision to continue, change or stop), deliverables, baselines, the change control system, and the subsidiary plans that make up the project management plan.
Predictive
This is the task's home ground: the whole project is planned in detail early, baselined, and executed and controlled against that plan.
Adaptive
Even in an adaptive organisation a predictive component may be needed, for example a fixed regulatory submission or a hardware purchase with long lead times inside an otherwise agile program.
  1. In practiceA provincial agency must replace a dam's spillway gates to a fixed engineering specification, with permits that name the exact design. Rosa, the project analyst, is asked which approach fits. The requirements are fixed, changes after fabrication would be very costly, and the regulator expects a documented, approved design before work starts. A predictive approach with phase gates fits best, with change control for any later change.
  2. Where questions turnAssuming the process groups are a strict sequence of phases. They are groups of activities that interact and repeat within each phase.
Practise PRD.1

PRD.2Read and build a predictive schedule: the WBS, work packages, the critical path and variance

  • The work breakdown structure (WBS) decomposes the total scope into deliverables and smaller pieces; it is deliverable oriented and follows the 100% rule (the children add up to all of the parent's work, no more and no less). The lowest level is the work package.
  • A work package is small enough to estimate cost and duration and to assign to one owner; the WBS dictionary describes each one (scope, owner, acceptance, cost). The scope baseline is the approved scope statement, WBS and WBS dictionary.
  • Work packages are decomposed into activities, which are sequenced (finish-to-start is most common) into a network, given durations, and turned into the schedule.
  • The critical path is the longest path through the network; it sets the shortest possible duration, and in a simple network its activities have zero total float. Total float is how long an activity can slip without delaying the project end; free float is how long it can slip without delaying the next activity.
  • The forward pass computes early start and early finish; the backward pass computes late start and late finish; float = late start - early start (or late finish - early finish).
  • Schedule variance SV = EV - PV: negative means behind schedule. Compression techniques: crashing adds resources to critical activities (more cost), fast tracking overlaps activities (more risk).
  • The quality management plan sets standards, metrics and checks for the deliverables; the integration side of the plan joins the subsidiary plans and the baselines so a change in one is checked against the others.
Predictive
The schedule is built bottom up from the WBS, baselined, and tracked against that baseline, with the critical path watched most closely.
Adaptive
Adaptive teams replace the detailed schedule with a release plan and iterations; the closest equivalent of a work package is a backlog item sized to fit in one iteration.
  1. In practiceA conference project has four activities: A (3 days, no predecessor), B (5 days, after A), C (2 days, after A) and D (4 days, after B and C). The paths are A-B-D (12 days) and A-C-D (9 days), so the critical path is A-B-D and the project takes 12 days. Activity C has 3 days of float, because it can slip three days before it delays D. If B slips by one day, the project end slips by one day.
  2. Where questions turnPicking the path with the most activities instead of the longest total duration, or forgetting that an activity with float can still become critical if it slips past its float.
Practise PRD.2

PRD.3Keep a predictive project under control with its artifacts and its cost and schedule figures

  • Predictive artifacts: the project management plan and baselines, the change log, change requests, the issue log, the risk register, the assumption log, the lessons learned register, status and variance reports, and the requirements traceability matrix.
  • Change control: a change request is documented, its effect on scope, schedule, cost and quality analysed, and the change control board (or the authority the plan names) approves or rejects it; approved changes update the baselines and the change log.
  • Earned value compares planned value (PV, the budgeted value of work scheduled), earned value (EV, the budgeted value of work actually done) and actual cost (AC). Budget at completion (BAC) is the total budget.
  • Cost variance CV = EV - AC and schedule variance SV = EV - PV: negative is unfavourable. Cost performance index CPI = EV / AC and schedule performance index SPI = EV / PV: below 1 is unfavourable.
  • Forecasts: estimate at completion EAC = BAC / CPI when current cost performance is expected to continue; estimate to complete ETC = EAC - AC; variance at completion VAC = BAC - EAC (negative means a forecast overrun).
  • Worked figures: BAC 100,000, PV 50,000, EV 40,000, AC 50,000 gives CV -10,000, SV -10,000, CPI 0.8, SPI 0.8, EAC 125,000, ETC 75,000, VAC -25,000.
Predictive
Control means measuring performance against the baselines, reporting variances, and taking corrective or preventive action through change control.
Adaptive
Adaptive teams control through short feedback loops (burndown and burnup charts, velocity, reviews); earned value can still be applied per release using story points as the measure of work done.
  1. In practiceA school renovation has a budget of 200,000. At the end of month four, the plan said 120,000 of work should be done, the work actually done is worth 100,000, and 110,000 has been spent. CV = 100,000 - 110,000 = -10,000 and CPI = 100,000 / 110,000, about 0.91, so the project is over budget; SV = 100,000 - 120,000 = -20,000 and SPI is about 0.83, so it is behind schedule. EAC = BAC / CPI = 200,000 / (100,000 / 110,000) = 220,000. The analyst reports the variances and the forecast to the project manager, who looks at the causes.
  2. Where questions turnSubtracting the wrong way round (AC - EV) or using PV in a cost variance. Both CV and SV start from EV: CV subtracts AC, SV subtracts PV (VAC is BAC - EAC).
Practise PRD.3

Key terms

Work breakdown structure (WBS)
A breakdown of all the project's scope, level by level, into deliverables and then work packages.
100% rule
The WBS includes all of the project's work and nothing else; each level's children add up to their parent.
Work package
The lowest level of the WBS, which can be estimated, scheduled and assigned to one owner.
Scope baseline
The approved scope statement, WBS and WBS dictionary, changed only through change control.
Critical path
The chain of dependent activities with the greatest total duration; it fixes how soon the project can finish.
Total float
How long an activity can be delayed without delaying the project's finish date.
Crashing
Shortening the schedule by adding resources to critical path activities, at extra cost.
Fast tracking
Shortening the schedule by doing activities in parallel that were planned in sequence, at extra risk.
Change control board (CCB)
The group with authority to approve or reject change requests to the baselines.
Planned value (PV)
The budget assigned to the work that was meant to be finished by a given date.
Earned value (EV)
The budget value of the work actually finished by a given date.
Actual cost (AC)
The cost actually incurred for the work completed by a given date.
Cost performance index (CPI)
EV / AC; below 1 means the work is costing more than planned.
Estimate at completion (EAC)
The forecast total cost; BAC / CPI when current cost performance continues.

After this guide: Given a short network or an earned value table, can you find the critical path and the float, compute CV, SV, CPI, SPI, EAC, ETC and VAC correctly, say what each result means, and name the artifact or the change step a predictive project uses next?

Practise Predictive, Plan-Based Methodologies

ExamDragon is independent exam preparation, not affiliated with, endorsed by, approved by or reviewed by the Project Management Institute (PMI). CAPM and PMI are registered marks of the Project Management Institute, Inc. The names are used only to describe the exam. Every question and guide here is our own, written from PMI's published CAPM Examination Content Outline (2023 Exam Update); the path is not a source of the 23 hours of project management education PMI requires.