CAPM study sheet · Domain 3

Agile Frameworks/Methodologies

Project Management Institute (PMI) Certified Associate in Project Management (CAPM)

5 tasks · PMI Examination Content Outline (2023 Exam Update)

Agile frameworks and methodologies is a fifth of the scored questions. It asks when an adaptive approach fits, how iterations are planned and tracked, which artifacts an adaptive team uses to stay in control, what makes Scrum, Extreme Programming (XP), Kanban and scaled frameworks such as SAFe different, and how a team defines done and orders its work by value. Questions usually describe a team at work (a sprint planning session, a burndown that flattens, a product owner reordering the backlog) and ask which event, role, artifact or practice it is, or what the team member should do. Know the Scrum roles, events and artifacts exactly, know that velocity is one team's own planning measure, and keep acceptance criteria (per item) apart from the Definition of Done (for every item).

You should be able to: Given a short scene from an adaptive team, can you name the role, event, artifact or framework at work, read a burndown or a board, plan from the team's own velocity, tell acceptance criteria from the Definition of Done, and order work by value?

Every task: the key point, the two approaches and the trap

  1. AGL.1 Know when an adaptive approach suits the work and the organisation

    An adaptive approach suits work with uncertain or changing requirements, where early feedback is valuable, the product can be delivered in usable pieces, and customers or users are available to review it often.

    Predictive: A predictive approach is the better fit when requirements are known and stable and change after delivery would be very costly.

    Adaptive: An adaptive approach is the better fit when the customer can only say what they want after seeing something work, and the team can deliver and learn in short cycles.

    Trap: Choosing agile because it sounds modern. The choice follows the work: stable, costly-to-change work suits predictive; uncertain, valuable-to-learn work suits adaptive.

  2. AGL.2 Plan iterations: slice the work, set the scope inputs and track progress the adaptive way

    An iteration (a sprint in Scrum) is a fixed timebox, commonly one to four weeks, that produces a usable increment that meets the Definition of Done; releases group the results of one or more iterations for delivery to users.

    Predictive: Predictive tracking compares progress with a baseline schedule and budget and often only shows a problem at a reporting period or a gate.

    Adaptive: Adaptive tracking shows progress daily (task board, burndown) and per iteration (velocity, review of the increment), so the plan adjusts quickly.

    Trap: Extending a sprint to finish unfinished work. The timebox is fixed; unfinished items go back to the product backlog to be reordered.

  3. AGL.3 Keep an adaptive project under control with its own artifacts

    The product backlog is the single ordered list of everything the product might need, owned by the product owner; the sprint backlog is the sprint goal, the items selected for the sprint and the developers' plan to deliver them; the increment is the sum of done work.

    Predictive: Control artifacts are documents and baselines: schedules, variance reports, change logs and status reports.

    Adaptive: Control artifacts are light and visible: the backlogs, the board, burndown and burnup charts and the increment itself, reviewed at the team's regular events.

    Trap: Blaming the team when a burnup shows a later forecast finish. Check both lines: if the completed-work line is climbing at its usual rate and the scope line has risen, the added scope, not the team's pace, pushed the finish out.

  4. AGL.4 Know the parts of the common adaptive frameworks: Scrum, XP, Kanban and scaled agile

    Scrum has three accountabilities (product owner, scrum master, developers), five events (the sprint, sprint planning, the daily scrum, the sprint review and the sprint retrospective) and three artifacts (product backlog, sprint backlog, increment).

    Predictive: Some predictive organisations adopt single practices such as daily stand-ups or a Kanban board for operations work without becoming adaptive overall.

    Adaptive: Teams choose the framework that fits: Scrum for product work in sprints, Kanban for continuous flow such as support requests, XP practices for software quality, SAFe when many teams build one product.

    Trap: Calling the scrum master the team's manager, or saying the product owner assigns tasks. The scrum master serves and coaches; the developers decide who does what.

  5. AGL.5 Define what done means for adaptive work and put tasks in order of value

    Acceptance criteria are the conditions a specific backlog item must meet to be accepted by the product owner; the Definition of Done is the shared quality checklist that applies to every item (for example code reviewed, tested, documented).

    Predictive: Predictive task management assigns activities from the schedule and measures percent complete; acceptance happens mostly at the end.

    Adaptive: Adaptive task management pulls tasks from the sprint backlog, finishes one before starting another, and accepts work item by item against its criteria.

    Trap: Treating acceptance criteria and the Definition of Done as the same thing. Acceptance criteria belong to one item; the Definition of Done applies to all of them.

Key terms

Product backlog:
The single ordered list of everything the product might need, owned by the product owner.
Sprint backlog:
What the developers take on for the sprint: its goal, the backlog items chosen and their plan for delivering them.
Increment:
A concrete, usable step toward the product goal that meets the Definition of Done and adds to every earlier increment; a sprint can produce more than one.
Product owner:
The person accountable for maximising the product's value and for ordering the product backlog.
Scrum master:
The person accountable for the team's effectiveness with Scrum, who coaches and removes impediments.
Sprint retrospective:
The event at the end of a sprint where the team inspects how it worked and plans improvements.
Velocity:
The amount of work one team completes per iteration, used by that team to plan.
Burndown chart:
A chart of work remaining against time in an iteration or release.
Burnup chart:
A chart of work completed against time, with a separate line for total scope.
WIP limit:
The maximum number of items allowed in a stage of a Kanban board at once.
Definition of Done:
The shared checklist of quality conditions every item must meet to be called done.
Acceptance criteria:
The conditions a specific backlog item must meet to be accepted.
Agile release train:
In SAFe, a long-lived team of agile teams that plans and delivers together.
Test-driven development:
An XP practice of writing an automated test before the code that makes it pass.