CAPM study sheet · Domain 2

Predictive, Plan-Based Methodologies

Project Management Institute (PMI) Certified Associate in Project Management (CAPM)

3 tasks · PMI Examination Content Outline (2023 Exam Update)

Predictive, plan-based methodologies is about a sixth of the scored questions. It asks when a plan-driven approach fits, what happens in each process group (initiating, planning, executing, monitoring and controlling, closing), how a schedule is built from the work breakdown structure through to the critical path, and how a predictive project is kept under control with its logs, baselines, change control and earned value figures. Expect calculations at the associate level: a small network with durations and predecessors to find the critical path or the float, and an earned value table to compute a variance or an index and say what it means. Read the figures carefully, use the formula exactly, and interpret the sign: a negative variance or an index below 1 is unfavourable.

You should be able to: Given a short network or an earned value table, can you find the critical path and the float, compute CV, SV, CPI, SPI, EAC, ETC and VAC correctly, say what each result means, and name the artifact or the change step a predictive project uses next?

Every task: the key point, the two approaches and the trap

  1. PRD.1 Know when a plan-driven, predictive approach suits the work and the organisation

    A predictive approach suits work whose requirements are clear and stable, where change late is costly, where regulation or contracts demand a defined scope and documentation, and where the deliverable cannot be used in pieces (a bridge, a plant, a regulated device).

    Predictive: This is the task's home ground: the whole project is planned in detail early, baselined, and executed and controlled against that plan.

    Adaptive: Even in an adaptive organisation a predictive component may be needed, for example a fixed regulatory submission or a hardware purchase with long lead times inside an otherwise agile program.

    Trap: Assuming the process groups are a strict sequence of phases. They are groups of activities that interact and repeat within each phase.

  2. PRD.2 Read and build a predictive schedule: the WBS, work packages, the critical path and variance

    The work breakdown structure (WBS) decomposes the total scope into deliverables and smaller pieces; it is deliverable oriented and follows the 100% rule (the children add up to all of the parent's work, no more and no less). The lowest level is the work package.

    Predictive: The schedule is built bottom up from the WBS, baselined, and tracked against that baseline, with the critical path watched most closely.

    Adaptive: Adaptive teams replace the detailed schedule with a release plan and iterations; the closest equivalent of a work package is a backlog item sized to fit in one iteration.

    Trap: Picking the path with the most activities instead of the longest total duration, or forgetting that an activity with float can still become critical if it slips past its float.

  3. PRD.3 Keep a predictive project under control with its artifacts and its cost and schedule figures

    Predictive artifacts: the project management plan and baselines, the change log, change requests, the issue log, the risk register, the assumption log, the lessons learned register, status and variance reports, and the requirements traceability matrix.

    Predictive: Control means measuring performance against the baselines, reporting variances, and taking corrective or preventive action through change control.

    Adaptive: Adaptive teams control through short feedback loops (burndown and burnup charts, velocity, reviews); earned value can still be applied per release using story points as the measure of work done.

    Trap: Subtracting the wrong way round (AC - EV) or using PV in a cost variance. Both CV and SV start from EV: CV subtracts AC, SV subtracts PV (VAC is BAC - EAC).

Key terms

Work breakdown structure (WBS):
A breakdown of all the project's scope, level by level, into deliverables and then work packages.
100% rule:
The WBS includes all of the project's work and nothing else; each level's children add up to their parent.
Work package:
The lowest level of the WBS, which can be estimated, scheduled and assigned to one owner.
Scope baseline:
The approved scope statement, WBS and WBS dictionary, changed only through change control.
Critical path:
The chain of dependent activities with the greatest total duration; it fixes how soon the project can finish.
Total float:
How long an activity can be delayed without delaying the project's finish date.
Crashing:
Shortening the schedule by adding resources to critical path activities, at extra cost.
Fast tracking:
Shortening the schedule by doing activities in parallel that were planned in sequence, at extra risk.
Change control board (CCB):
The group with authority to approve or reject change requests to the baselines.
Planned value (PV):
The budget assigned to the work that was meant to be finished by a given date.
Earned value (EV):
The budget value of the work actually finished by a given date.
Actual cost (AC):
The cost actually incurred for the work completed by a given date.
Cost performance index (CPI):
EV / AC; below 1 means the work is costing more than planned.
Estimate at completion (EAC):
The forecast total cost; BAC / CPI when current cost performance continues.

ExamDragon, examdragon.com/capm. Independent exam preparation, not affiliated with, endorsed by or reviewed by PMI; written in our own words from PMI's CAPM Examination Content Outline (2023 Exam Update). CAPM and PMI are registered marks of the Project Management Institute, Inc.